Tejaji Nagar–Balwara Section — NH-347DG, Madhya Pradesh

Tejaji Nagar–Balwara Section — NH-347DG, Madhya Pradesh

This project involves one-time improvement works on the existing Tejaji Nagar to Balwara section of NH-347DG, identified as Indore to Boregaon Package-II, in Madhya Pradesh. The documented project length is 22.52 km. The work is being undertaken for the National Highways Authority of India, Regional Office Bhopal, under an item-rate contract. The contract value recorded in the ongoing-project statement is ₹69.68 crore, with the contract dated 20 July 2026. The stipulated completion period is 12 months from the appointed date. The appointed date had not been declared in the supplied statement, so a calendar start or completion date is not available. The full ₹69.68 crore is recorded as the value of work remaining to be completed, with an escalation factor of 1.00. The project adds ongoing highway improvement work in Madhya Pradesh to Suraj Construction Company's portfolio and covers a clearly defined 22.52 km section of NH-347DG.

Project Details:

  • Project Type:One-Time Improvement of Existing Highway
  • Project Category:Not specified
  • Client:NHAI Regional Office, Bhopal
  • Project Location:Madhya Pradesh
  • Contract Value:₹69.68 Cr
  • Date of Completion:12 months from appointed date
  • Execution Information:Item Rate Basis
  • Project Scope:One-time improvement of the existing Tejaji Nagar to Balwara section of NH-347DG (Indore to Boregaon Package-II), covering a length of 22.52 km, in Madhya Pradesh.
  • Authority:National Highways Authority of India
  • Project Status:Ongoing
Start Your Project

Interested in a project like this?

Our team is ready to discuss tenders, quotations, and partnership opportunities. Let's build something remarkable together.